Benny the Jet Rodriguez said:
Half a billion huh?
https://www.opportunitylouisiana.gov/news/meta-commits-more-than-50-billion-for-north-louisiana-project-becoming-one-of-the-largest-data-centers-in-history
I have no idea what your point is supposed to be. Like every commercial or industrial project, they can vary by scale and size. I just named a mid range / average project.
Total Cost by Facility Scale
Edge / Small-Format (500 5,000 SF): $6 million to $30 million. Typically modular or containerized setups used for localized data processing.
Enterprise / Mid-Scale (10 50 MW): $80 million to $600 million. Standard corporate or retail colocation facilities.
Hyperscale / Tier IV Campus (100+ MW): $900 million to $1.5+ billion. Massive, highly redundant multi-building campuses built by tech giants like Microsoft, Google, and Amazon