I have been keeping a list with expected completed dates. But things are almost never completed when they say they will. For example, the guy that came to fix our shutters. He came on the agreed upon day and replaced them but needed to come back a second day because he did not have the correct paint color. Stuff like this has happened over and over again where people come to work on something and they don't entirely know what they are supposed to be doing.
But here is the what I think is the most up-to-date list I have.
I don't know if I am being unreasonable with all this but we paid $425K for the house and it does not look or feel like a $425,000 house.
FULL LIST PENDING ITEMS :A) ***Leveling of the Backyard***
STILL PENDING [Previously scheduled for 09/22/2023; Hole filled 11/10/2023] [Pending Drainage Issue; See Item II]B) Hole at left side of the backyard with exposed PVC piping.
COMPLETED 11/10/2023C) The left side of the front yard/side yard is uneven
COMPLETED 10/06/2023D) Section 4 of sprinkler system has a busted/broken head
COMPLETED BY MY LANDSCAPING GUY 03/15/2024 [Previously scheduled for 09/22/2023]E) Broken black water meter box in side yard.
COMPLETED 10/06/2023F) High and slanted cement block for City Water Access
COMPLETED 10/13/2023G) Attic Door in Garage does not recoil to close.
COMPLETED 09/15/2023H) Unpainted wood under the oven.
COMPLETED 09/09/2023 I) The shoe molding in kitchen is different color stain and not appropriately cut
COMPLETED 10/20/2023J) Trash can drawer needs to be soft closed.
STILL PENDING [No timeline set]K) Loose kitchen drawer
COMPLETED 09/01/2023L) Missing lower cabinet shelves
COMPLETED 10/20/2023M) Slanted Upper Cabinet Shelves. It appears that two of the metal pieces that go in the holes to hold the shelf up are misshapen.
COMPLETED 09/26/2023[Cabinet Guy on 09/09/2023 said he is addressing] [Cabinet guy came 09/26/2023 and fixed the pieces holding up the shelves. Was also able to address protruding screws but Painter will need to come to cover up holes]N) Poorly painted items in Kitchen, including fake "drawer" under the cooktop, left side of cabinets, under island overhang.
COMPLETED 09/09/2023 O) Dishwasher is leaning backwards causing the lower rack to slide back in when open
COMPLETED 09/15/2023P) "Dirtier"/Darker grout on kitchen backsplash
COMPLETED 11/10/2023Q) Chip on the kitchen island countertop (Crack is now present; see Item CC).
COMPLETED 11/10/2023R) The outlets on the wall in the Primary Bedroom for the TV are not centered.
COMPLETED 09/15/2023 with Drywall completed 09/22/2023S) The soft close drawer in the Primary Bath is still missing
COMPLETED 09/26/2023T) The other vanity is not touching the floor. There is a small piece of wood holding it up.
COMPLETED 11/10/2023U) Dark spot on one of the shower tiles
At this point, just forget this oneV) A wall by the toilet door is not textured.
COMPLETED 09/22/2023W) The front left bedroom has a "ghost door" at the closet
COMPLETED 11/17/2023X) The Jack-and-Jill bathroom at the front of the house continues to randomly "run."
COMPLETED 11/17/2023Y) The water valve in this bathroom is still not secured appropriately to the wall.
COMPLETED 11/17/2023Z) There are multiple (and I mean lots of) places throughout the home where paint has bled onto other surfaces. The main example is there are many white outlets that have gray paint on them. Baseboards have gray paint on them. Door stops have white paint of them. Light Switch covers have gray paint on them. Shoe molding has green kitchen paint or gray wall paint.
COMPLETED 04/04/2024AA) Missing hot + cold valves for future outdoor kitchen on column
COMPLETED 09/09/2023 + 10/10/2023BB) Backward bending door at Game Room
COMPLETED 11/10/2023 NEWER ITEMS :CC) Full crack on Kitchen Island Countertop
STILL PENDING [Put in Warranty Dept on 09/19/2023; Perry was supposed to come out to see it on 09/22/2023 but did not come until the next week. We have been told it is a fissure as it does not go all the way through. There are other noticeable fissures on the slab and this one is different. I have had multiple workers confirm it is a crack and even gotten an estimate from a general contractor confirming the crack and pricing to fix]DD) Shoe Molding by entrance is coming apart.
STILL PENDING [Workers came 02/02/2024 to fix; painters came to caulk 04/02/2024; when hole behind baseboard was covered, the shoe molding came apart again.]EE) Crack at Bedroom #2 window despite screen
STILL PENDING [Discussed with Peter on 12/15/2023 and says will fix as this is due to poor installation]FF) Hole in ceiling by pendant at kitchen island
STILL PENDING [Workers came 02/02/2024 to fix but did not have correct tools/paint]GG) Chipping paint and wood not painted on kitchen island
STILL PENDING [Workers came 02/02/2024 to fix but did not have correct paint despite being told of green color; they did caulk it to seal]HH) Cracked Curb
COMPLETED but left crumbled pieces in road [Caused by Worker Trucks; Peter had discussed they would address this once construction on our street was completed…]II) Our Backyard continues to pool and collect water
[See Item A] STILL PENDING [Discussed with Peter on 12/15/2023 and he said he would have two drains installed taking water to the street. Landscapers came on 02/02/2024 to take measurements and pictures. Now I am being told this will not happen?!?]JJ) Shutters at front of home are coming apart [See Attached Picture]
COMPLETED 04/13/2024KK) Floor boards separating by Bedroom #3 (Guest Bedroom)
COMPLETED 04/12/2024LL) For
Item DD, when the workers came to fix and pulled the baseboard back, there was a
HOLE in the sheetrock. Workers mentioned that water may have entered the home and the sheetrock should extend to the ground. It currently does not.
COMPLETED 04/12/2024 [PLEASE SEE ITEM DD FOR PENDING ISSUE]MM) No Irrigation Shut Off Valve found
STILL PENDING [Valve installed/found 04/09/2024, notice from City of Conroe about continuous water usage 04/10/2024; Workers scheduled for 04/19/2024] -FTA c/o 2013