Reload84 said:
Good discussion on this board about these issues. Here's another take from Politico's E&E News (Energy & Environment) on the Senate Hearing last week and the politics at play: https://www.eenews.net/articles/texas-regulators-urged-to-halt-33b-transmission-plan/
That's certainly a lot more informative that the link that appeared elsewhere in this thread. Some highlights:
Quote:
The first of the $33 billion of transmission projects was meant to funnel power to West Texas to help support oil and gas production. The Permian region across Texas and New Mexico accounted for about 44 percent of U.S. oil production and 19 percent of natural gas output last December, according to federal data.
The industry for years has been lobbying Texas to build more transmission lines to the Permian after hydraulic fracturing, or fracking, and other techniques sent production skyrocketing. Electricity is needed for those advanced operations, and data center plans would only add to the power demand in Texas.
"Part of this [problem] is because [transmission] wasn't built when it was needed," said Todd Staples, president of the Texas Oil and Gas Association. "No one believed that oil and gas was going to grow 430 percent in production in the Permian Basin since 2015 to 2025."
So, the line in question is not a data center boondoggle, after all. They might benefit, but the whole reason the project got started was because of the O&G activity in the Permian. Here's the part that is worth a second look:
Quote:
Before HB 5066, ERCOT relied on independent and in-house modeling along with some data from transmission service providers to come up with transmission plans.
At Wednesday's hearing, ERCOT Chief Operating Officer Woody Rickerson said HB 5066 requires the grid manager to rely on transmission companies' data for the Permian Basin Reliability Plan and other transmission projects.
He said demand forecasts from those providers were "substantially higher" than ERCOT's in-house forecasts.
Transmission service providers earn a guaranteed rate of return on the transmission projects they build, and the bigger and more expensive a project is, the more profit they make.
Still, the O&G people are adamant that the line is needed. So, what's all the uproar about? It's just garden variety NIMBY stuff.
Quote:
Part of their frustration stems from HB 5066, which also cut the timelines for the PUC to approve or deny transmission project from one year to 180 days. That gives landowners less time to argue for other routes that would bypass their land.
More than 200 people spoke out against the process to fight the transmission lines at Wednesday's hearing in Austin, Texas, including country music legend Tanya Tucker. She belted out the chorus of her 1978 hit "Texas (When I Die)."
"I'm very disappointed in how this has been handled," Tucker said. "This isn't the way we do things in Texas. You don't rush in and turn someone's life upside down."
The pushback against the lines has been so intense that multiple senators at Wednesday's hearing called for stopping the build-out until the state Legislature can weigh in on the issue.
As someone whose family has been ranching in Archer County since 1890, I've had experience with various electric line and pipelines coming across our property. But, we are in the ranching business, not hobby farming, or owning a few acres for rural solitude. We had a couple of gas pipeline projects come through in the last few years, and I was disappointed that one of those projects was exclusively on my cousin's property, and most of the other one was, too, because those right of way checks were nice paydays for projects which had little long term impact on ranching, or even hunting (which we lease out).
I can understand why folks who do other things with their land are more sensitive about this stuff, but Texas has never been a state where NIMBYism had the upper hand. If it ever becomes one, we are in trouble.