Beltway 8 bridge issues from same bridge firm that cause Florida collapse

7,722 Views | 40 Replies | Last: 4 yr ago by MouthBQ98
BAP Enthusiast
How long do you want to ignore this user?
https://www.chron.com/news/houston-texas/transportation/article/beltway-8-ship-channel-bridge-16666578.php

Quote:

The engineering firm and contractor behind the designs, FIGG Bridge Group, attempted a new technique after winning its bid to replace the old span, which was built in 1982. FIGG's new construction method involved fabricating sections of new roadway on the ground and hoisting the segments into place. Work on the new Beltway 8 Bridge began in 2018, the same year another FIGG-constructed bridge collapsed near Florida International University in Miami, killing six people and putting the company's practices into question.


Since this engineering firm is of course full of """"female engineers"""" they probably got tons of these types of jobs. Which idiots should we blame for not immediately firing these morons from this job.

Just absolutely incredible that they are still working. I know I'm never going to feel safe driving over that bridge now.
Highway6
How long do you want to ignore this user?
We can only hope for a "mostly peaceful" collapse
fullback44
How long do you want to ignore this user?
I won't be driving on that new bridge anytime soon ….
Picard
How long do you want to ignore this user?
Build Back Better?

B-1 83
How long do you want to ignore this user?
Isn't that the same one that was building the new bridge over the Corpus ship channel?
Being in TexAgs jail changes a man……..no, not really
nortex97
How long do you want to ignore this user?
First, are we sure this isn't a racist bridge?
Fightin_Aggie
How long do you want to ignore this user?
Why fabricate on site? This makes no sense to me. The fabrication process is pretty exacting and reguires several days to cure and setup in additional to specialized equipment.

It just seems stupid
The world needs mean tweets

My Pronouns Ultra and MAGA

Trump 2024
evestor1
How long do you want to ignore this user?
Female engineers likely have zero to do with bad work.

Having company Executive officers and senior management focused on diversity rather than results likely has direct correlation of bad work.
MouthBQ98
How long do you want to ignore this user?
Nothing wrong with competent and qualified female engineers.

The problem is the favorable selection of engineering candidates and engineering employees and engineering business based on identity politics instead of demonstrated competency and ability.

Gender doesn't determine individual ability with respect to intellectual pursuits, but it is a poor selection criterion when competency is potentially a life or death matter.
Marcus Brutus
How long do you want to ignore this user?
Hey, wait until the docs from the woke med schools start graduating and practicing. Gonna be bad.
Buying_time
How long do you want to ignore this user?
Competency is race and gender blind.

When quotas are mandated - businesses will game the system to get work. It is all about the mean green.
Definitely Not A Cop
How long do you want to ignore this user?
A buddy that does design work over on Houston has been talking about this for years. As soon as the bridge in Florida collapsed, another firm basically took the design for the beltway bridge and reviewed the engineering from the ground up. I wouldn't worry too much about it, anymore than you usually do driving over a bridge like that.
Squadron7
How long do you want to ignore this user?
Falling bridges are just eggs broken to make the Utopian omelette.
Marcus Brutus
How long do you want to ignore this user?
I did a search, linked in, etc and don't really see any wokeness being pushed by Figg.
Ag with kids
How long do you want to ignore this user?
B-1 83 said:

Isn't that the same one that was building the new bridge over the Corpus ship channel?
Yep.

Which is why they stopped work on it. TxDOT wanted FIGG removed from the contract. Don't know the status of that demand but doesn't look like they've worked on it in awhile.
fixer
How long do you want to ignore this user?
Glad there was some original thinking going on and looking into the issue somewhat proactively. Bridge collapses are awful.
BaileyAg
How long do you want to ignore this user?
nortex97 said:

First, are we sure this isn't a racist bridge?
BAP Enthusiast
How long do you want to ignore this user?
Ag with kids said:

B-1 83 said:

Isn't that the same one that was building the new bridge over the Corpus ship channel?
Yep.

Which is why they stopped work on it. TxDOT wanted FIGG removed from the contract. Don't know the status of that demand but doesn't look like they've worked on it in awhile.


Good. TxDOT appears pretty good on things like this.
fixer
How long do you want to ignore this user?
Fightin_Aggie said:

Why fabricate on site? This makes no sense to me. The fabrication process is pretty exacting and reguires several days to cure and setup in additional to specialized equipment.

It just seems stupid
Yep... I wonder what the weld inspection plan was.

Stat Monitor Repairman
How long do you want to ignore this user?
CCP Joe Veggie said:

Hey, wait until the docs from the woke med schools start graduating and practicing. Gonna be bad.
The entire covid response has been the biggest groupthink failure of all time.

Don't know how you can get much worse.

Hysteria prevailed over science and reason.

Dissenters were silenced and shadow banned like engineers that objected to the Challenger launch.
Fightin_Aggie
How long do you want to ignore this user?
Fightin_Aggie said:

Why fabricate on site? This makes no sense to me. The fabrication process is pretty exacting and reguires several days to cure and setup in additional to specialized equipment.

It just seems stupid
https://bayoubeatnews.com/2021/12/unfinished-beltway-8-bridge-over-houston-ship-channel-to-be-demolished-due-to-significant-flaws/

I don't live in Houston so needed some background on the bridge
The world needs mean tweets

My Pronouns Ultra and MAGA

Trump 2024
Agman
How long do you want to ignore this user?
Why is the county on the hook for the costs? The design firm and their insurance should have to cover, no?
Icecream_Ag
How long do you want to ignore this user?
Agman said:

Why is the county on the hook for the costs? The design firm and their insurance should have to cover, no?
probably because the county is full of the dumb and agreed to a "no buyout clause" for lack of a better term, that states the county is responsible for costs if the contract is terminated for any reason
Sea Speed
How long do you want to ignore this user?
I'm pretty sure they are tearing the bridge down and restarting. The taxpayers are on the hook for 50 mil for demo. Unbelievable.
AggieKatie2
How long do you want to ignore this user?
Only thing I'm not wild about is the same entity that did the study on FIGGS work is the same one that was awarded the job. Seems like a conflict of interest.
Emotional Support Cobra
How long do you want to ignore this user?
When engineers argue, do they glare at their own shoes or each other's?
YouBet
How long do you want to ignore this user?
Ag with kids said:

B-1 83 said:

Isn't that the same one that was building the new bridge over the Corpus ship channel?
Yep.

Which is why they stopped work on it. TxDOT wanted FIGG removed from the contract. Don't know the status of that demand but doesn't look like they've worked on it in awhile.
Well, that's interesting. Been wondering what was going on with that. Concerning considering the scale of that bridge.
Aggie_Boomin 21
How long do you want to ignore this user?
FIGG only designed the free span over the water, which is structurally the most challenging/demanding but it isn't that long. Not sure if they found someone else to redo or back check the design of that span.
annie88
How long do you want to ignore this user?
nortex97 said:

First, are we sure this isn't a racist bridge?


Yes, Pete Buttigieg has been warning us about these racist civil engineering projects.
Currently a happy listless vessel and deplorable. #FDEMS TRUMP 2024.
Fight Fight Fight.
annie88
How long do you want to ignore this user?
Which part of the beltway in Houston is
this on?
Currently a happy listless vessel and deplorable. #FDEMS TRUMP 2024.
Fight Fight Fight.
BAP Enthusiast
How long do you want to ignore this user?
annie88 said:

Which part of the beltway in Houston is
this on?


Over the ship channel I believe
Bigballin
How long do you want to ignore this user?
Yes. It's over the ship channel.
annie88
How long do you want to ignore this user?
BAP Enthusiast said:

annie88 said:

Which part of the beltway in Houston is
this on?


Over the ship channel I believe
Well at least that's a part I never go to. I live in Bryan now but I occasionally hit Houston for different areas or scoot over to Galveston some. But even when I live there I never really went there.

But still that's not cool.
Currently a happy listless vessel and deplorable. #FDEMS TRUMP 2024.
Fight Fight Fight.
BuddysBud
How long do you want to ignore this user?
AggieKatie2 said:

Only thing I'm not wild about is the same entity that did the study on FIGGS work is the same one that was awarded the job. Seems like a conflict of interest.


Conflict of interest is the Dora way, as long as she gets her cut.
CDUB98
How long do you want to ignore this user?
I wonder how many of you questioning a person's abilities and competency are engineers.

Gender and/or skin color have jack squat to do competency. Y'all are an embarrassment.

Have any of you ever thought that maybe, just maybe, the reason you see so many white and Asian male engineers is simply due to numbers?

Good gawd, I swear some of you jackwagons post like you wish it were still the 1950s.