agdx88 said:
Thanks. It's underground service so no mast through the roof.
I'll have him ask what type of panel and get that added to the quote.
I assume that CenterPoint will need to come pull the meter for this work. If so, wouldn't they will require a permit and an inspection before they reinstall the meter?
I also asked Claude about this and its response was about mid-range for price.
You will need to set that up if he is not. A permit is required for the meter pull and for the panel upgrade as well. With the approvals and timing required, i am surprised he is not handling the permit and meter pull/restore process. Does he plan to just walk away with a check in hand before the panel is inspected and power is restored? I wouldn't pay him in full until my power was back on and every breaker is confirmed working. Same for your new pool box. Money is your best leverage to get him to fix something if its not working right, so dont pay in full upfront (Big red flag if he demands this) and dont pay him out in full (Assuming either he fronts it all and you pay at end or a 50/50 to cover parts purchase at start and pay rest at end) till you are satisfied with the full job completed.
Permitting Process in Sugar Land
- Permit Requirement: The City of Sugar Land requires a permit for electrical service modifications, such as replacing a breaker panel.
- Application: Contractors or homeowners apply online through the Sugar Land Citizen Self Service Portal. A Residential Electrical Service Express permit typically covers service equipment changes without requiring detailed plan submittals.
- Licensed Electrician: Electrical work in Sugar Land must be performed by a licensed electrician who can pull the permit on your behalf.
CenterPoint Energy Coordination
- Power Disconnect/Reconnect: CenterPoint controls the electric meter and drop. Your electrician must coordinate with CenterPoint to temporarily cut power at the meter during the swap.
- Inspection First: The City of Sugar Land must inspect and approve the new panel installation before CenterPoint will restore power to the meter.